USACE / NAVFAC / AFCEC / NASA UFGS-01 11 00 (August 2011)
-------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-01 11 00 (January 2008)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated January 2014
SECTION 01 11 00
SUMMARY OF WORK
12/14
NOTE: This guide specification covers the requirements for a description of work covered in this contract and
is required for use in all projects.
Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide
specification or preparing new project specification sections. Edit this guide specification for project specific
requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert
appropriate information.
Remove information and requirements not required in respective project, whether or not brackets are present.
Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted
as a Criteria Change Request (CCR).
PART 1 GENERAL
WORK COVERED BY CONTRACT DOCUMENTS
Project Description
NOTE: Describe the project and the types of work involved in sufficient detail so as to present a general picture
which is self contained but does not refer to the drawings or to other parts of the specification. Mention peculiar
or hazardous work, and monitoring of archaeological resources. Do not provide quantities in the description.
The work includes [_____] and incidental related work.
Location
NOTE: Include station name and geographic location in the blank provided.
The work is located [at the _____], approximately as indicated. The exact location will be shown by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.