The project non-federal sponsors are required to complete the remaining two segments of the project, Morgan Shoals (45th to 51st Street) and Promontory Point segment (54th to 56th Streets), with Corps oversight at their expense to fulfill their obligations under the existing PCA. However, WRDA 2022 language directs the Corps to cost share the Locally Preferred Plan for those two remaining segments.
A Third-Party Review of the Promontory Point segment of the project was federally funded in 2022 at $450,000 through BIL. The review will investigate historic rehabilitation of the segment with respect to the Secretary of Interior’s Standards.